Bricks - End day 3 - Wed 27/8.

Wed 27/8. Some snaps at the end of day 3 bricking.
.

Nth side.
.

Rear Alfresco & Rumpus walls now 3/4 done.
Note, Tiles still not laid over Rumpus & Alfresco. I'm really hoping these are done in time for next rain...!!!
.

Bricking just starting to creep around onto the Sth side.
.

My not-so-straight garage pillar..! Report it to PD..?
..


Pipe works. Gas (yellow) coming from gas meter on other side of house to new location for hot water service (against pantry wall). Other thicker pipe is (i think) for solar hot water.
.

4 comments:

Petal said...

Bricks are coming along nicely. As for the pillar....don't want to sound negative, but it looks crooked to me, so I'd mention it now, so they know you're not satisfied with it - better to have it resolved now than leave it, I think.

Toni said...

Definitely mention the pillar to PD, it looks pretty crooked to me too.

Surprised at how much they've done in such a short time! You'll take over us at this rate.

Bricks/mortar look great!

DeGaul said...

Guys. Thanks for your input & recommendations. I rang SS this morning, and he was quick to state that "if it's bowed, it will be repaired".

Visited the site tonight, and sure enough, and faulty pillar had been pulled down.

Glad to see that tiles have now been laid over back rooms.

Toni said...

Great that they fixed the pillar straight away!

Wow tiles over your home theatre/rumpus? We didn't have them a week ago. Wonder why they don't tile that roof when they do the main roof?